Evaluation of CTCLS Series Traffic
Signal Load Switches in the Field — Bulb Life Determinations, and Development
of a Group Relamping Model
Authors:
Report Number: FHWA/OH – 2003/011
for copies of this report, go to:
http://www.dot.state.oh.us/divplan/research
or call 614-644-8173
Ohio Department of Transportation
Project Description
Problem
Maintaining
traffic signals is a significant expense at ODOT. Bulbs fail and need immediate replacement,
which entails the expense of traffic control and may involve hazards such as heavy
traffic or inclement weather conditions.
Two
possible technologies to reduce this problem are improved load
switches and group relamping.
The
improved CTCLS series load switches were developed by Conservation Load Switch
(CLS) of
Group relamping is the process of replacing all traffic signal bulbs
at a fixed interval, rather than simply waiting for them to fail before
replacement. Most of the useful life can
be obtained from the bulbs, while the cost of changing bulbs is reduced by
replacing them all at once instead of making several spot replacement
trips. The occasional failures that do
occur before the group relamping interval is up are
replaced immediately, but these are minimized because bulbs are not kept to the point where failures become
common.
Objectives
The
original objective was to assess the effect of the CTCLS load switches on bulb
life in the field on four different major brands of bulbs as used in six states
in varied climate regions in the
The
final objectives were to determine the best brand of bulb for use with
conventional load switches and to develop a
group relamping
model that could be used to determine the group relamping period that would minimize traffic signal
maintenance costs.
Description
Approximately
144 intersections in each state were selected for the test, half to use CTCLS
load switches and half to use conventional switches. Each state used a different brand of bulb as
follows:
After
installation, a number
of the CTCLS load switches gave dual indications or other malfunctions in the
field. It was eventually decided by the
lead state (
Whenever
a bulb failed, it was to be tagged by maintenance personnel and then sent to
the study subcontractor, the Operator Performance Laboratory at the
Additionally,
another spreadsheet was developed at ORITE to model group relamping. The spreadsheet would take as input various costs, distances involved in emergency spot and group relamping, and bulb survival rates (taken from existing
study records for the example in the report).
The output would be a table of annual cost of group relamping,
averaged over a ten year period, as a function of group relamping
interval in the range of 1 to 24 months.
The optimum group relamping interval can then
be found by selecting the interval with the minimum annual cost. A sensitivity analysis was conducted by
modifying the values of the input parameters to see how the output
changed.
Conclusions &
Recommendations
The CLS claims that their CTCLS series load switches
extended bulb life and reduced maintenance costs could not be investigated
since the switches were removed early in the study.
Overall,
the bulb life portion of the study produced little useful data. In all cases, the states and cities tagged
and returned at most a fraction of the failed bulbs. It appears that the extra work caused by the
study may have been asking too much of already busy maintenance personnel. Thus it seems that even well designed studies that rely
on extra efforts by field personnel over a long period of time are at best
difficult to carry out.
The Duro-test bulb manufacturer went bankrupt after the study
was underway, making the results from Iowa at best academic, since the bulb
would be no longer available for use by state DOTs.
Ohio used GE-Real bulbs, which had an extremely poor
field performance, with nearly 4% (3.99%) failing by the end of the first year,
nearly twice ODOT’s 2% maximum failure amount after
one year. It can be concluded that the
GE-Real bulb is not satisfactory and should not be used in
In
The group relamping model
was evaluated, using Ohio District 4 as a test case for a limited sensitivity
analysis. The model shows a relatively
shallow minimum at about 10 months, providing a minimum annual cost of $38,719
to the district for maintaining their 273 signalized intersections.
Implementation
Potential
Group relamping
spreadsheet esults will vary somewhat in other
districts or states, but the software can be applied to those cases as
well. The greatest difficulty involved
with the software is the need to input the emergency spot relamping
distances from the central office or garage to each signal, to cluster the
signals into groups that can be group relamped in a
single day, to input the distances to each cluster, and to input the distances
between the signalized intersections within each cluster.
The
software will provide a relamping interval that
minimizes overall cost, and an estimate of that cost on an annual basis based
on group relamping intervals from